Temple progress

A record of the work at Bargi, newest first. The trust posts here whenever a stage begins or ends, with photographs from the site.

  1. Next

    Walls of the Sreekovil and the mandapa

    Work resumes once the materials for the walls are funded. ₹2.9 lakh of ₹58 lakh has been received so far.

    Sponsor materials
  2. Aug 2025
    Foundation completed

    Plinth

    Foundation completed

    The stone foundation and plinth of the temple are now complete. Further work is waiting on funds for materials.

  3. Jul 2025
    Stone masonry foundation rises

    Stone masonry

    Stone masonry foundation rises

    Granite stone masonry was built up from the concrete bed to form the foundation walls.

  4. Jul 2025
    Concrete bed laid for the sanctum

    PCC bed

    Concrete bed laid for the sanctum

    A plain cement concrete bed was laid at the base of the excavation to receive the stone foundation.

  5. Jun 2025
    Excavation for the foundation

    Excavation

    Excavation for the foundation

    Trenches for the foundation were dug by hand along the marked lines.

  6. Jun 2025
    The temple plan is marked out on site

    Site marking

    The temple plan is marked out on site

    The outline of the Sreekovil, mandapa and surrounding structures was marked on the land at Bargi following the Kerala architectural plan.